U.S. Bank Stadium's fallen panel replaced, Mortenson Construction vows improvements

The facade will be reinforced to prevent further damage, the project's contractor said.

December 28, 2016 at 11:48PM
One zinc panel from U.S. Bank Stadium's problematic western prow fell to the ground early Monday while others have come loose again, leaving an absent horizontal strip of black panel from the glass facade to underneath the U.S. Bank Stadium logo.
One zinc panel from U.S. Bank Stadium’s problematic western prow fell to the ground early Monday while others have come loose again, leaving an absent horizontal strip of black panel from the glass facade to underneath the U.S. Bank Stadium logo. (Star Tribune/The Minnesota Star Tribune)

Workers have repaired a missing strip of zinc paneling that fell from U.S. Bank Stadium's western prow on Monday, prompting building contractor M.A. Mortenson Construction to reinforce the facade in hopes of preventing further damage from high winds.

Mortenson executive John Wood said Wednesday that the company, along with subcontractor McGrath, will install additional fasteners to exterior panels in the coming weeks.

"Our experts and the outside consultants who have studied the problem are confident in this solution," said Wood, who added that the repairs would not disrupt any events at the Minnesota Vikings' new home.

The announcement comes two days after "extreme weather and high winds" caused panels to "partially disengage," according to a statement from the Minnesota Sports Facilities Authority (MSFA). But one panel fell to the ground in the hours after midnight Monday.

Representatives from Mortenson and McGrath, who installed the panels, spent two days investigating the damage — visible from the glass facade to underneath the U.S. Bank Stadium logo that appears on the 270-foot high prow. No one was injured when the panel fell during the overnight hours.

Both moisture and wind have previously caused trouble for the $1.1 billion building that opened in August. Thousands of zinc panels that line the exterior have been the focus of a couple of concerns on the building.

Initially, the panels were bolted down only along the bottom edge. After heavy storms last summer, some panels came loose and flapped in the wind. Mortenson workers then reinforced the panels along the top edge.

The building, $489 million of which was covered by the taxpayers, is under warranty by Mortenson for two years.

Liz Sawyer • 612-673-4648

] Mark Vancleave - mark.vancleave@startribune.com * A day after strong winter winds raked the Twin Cities a number of panels were discovered to have fallen from the new U.S. Bank Stadium on Tuesday, Dec. 27, 2016.
U.S. Bank Stadium, which has had previous troubles caused by wind and moisture this year, is under warranty by Mortenson for two years. (The Minnesota Star Tribune)
about the writer

about the writer

Liz Sawyer

Reporter

Liz Sawyer  covers Minneapolis crime and policing at the Star Tribune. Since joining the newspaper in 2014, she has reported extensively on Minnesota law enforcement, state prisons and the youth justice system. 

See More

More from Minneapolis

card image

From small businesses to giants like Target, retailers are benefitting from the $10 billion industry for South Korean pop music, including its revival of physical album sales.