Last Minnesota leg of $2.1 billion electricity mega-project done

Growth in renewable energy, especially wind, driving multistate project, Xcel says.

September 27, 2016 at 2:27AM
Construction crews strung lines on new power poles not far from Mark Koepp's Bell Plaine farm. Mark Koepp, a hog farmer outside of Belle Plaine, is one of several affected landowners with concerns about the line. Crews have erected five towers on his 134-acre farm, and another seven on nearby land he rents. Construction crews have been disruptive and careless, Koepp said, damaging soil and tile lines with drilling and cement trucks. Koepp said he is not confident he will be repaid for the damage
Construction in 2013 of the multistate CapX project near Belle Plaine. The final Minnesota phase of the 345-kilovolt line from Hampton, Minn., to La Crosse, Wis., has been switched on. (The Minnesota Star Tribune)

A consortium of electric utilities recently completed the last Minnesota leg of a $2.1 billion transmission mega-project: a 156-mile power line from Dakota County through Rochester and on to La Crosse, Wis.

The CapX2020 project, which has been under construction for about six years, covers four states and includes 725 miles of new high-voltage lines. It's the biggest electricity transmission project in Minnesota since the 1970s, and it's aimed partly at freeing up power line capacity for the Upper Midwest's burgeoning wind energy industry.

"We have made great strides forward for wind," said Teresa Mogensen, senior vice president for transmission for Minneapolis-based Xcel.

Eleven days ago, the final phase of the 345-kilovolt line from Hampton, Minn., to La Crosse was switched on — "energized" in power line lingo. Executives from Xcel and its partners feted the $485 million project Monday at a substation in Hampton, which is about 35 miles southeast of downtown Minneapolis.

The Hampton-Rochester-La Crosse line is jointly owned by Xcel, Southern Minnesota Municipal Power Agency, La Crosse-based Dairyland Power Cooperative, Rochester Public Utilities and Sun Prairie, Wis.-based WPPI Energy. The new line is the fourth of five transmission projects within CapX2020.

One is still under construction, a segment in eastern South Dakota from Brookings to Big Stone. It's due to be completed next year.

CapX2020 developed out of a hallway conversation at a 2004 industry meeting between executives of Minnesota's two largest power companies, Xcel and Maple Grove-based Great River Energy. Nine more utilities would join them for the entire project, which also features lines from Fargo to Monticello, Minn., and Bemidji, Minn., to Grand Rapids, Minn.

The project was opposed by citizens groups who argued that with power demand falling, expensive new transmission lines weren't needed. Costs of transmission lines are passed down to customers through electricity bills.

Indeed, electricity demand has been stagnant since the 2008 economic meltdown. But the strong growth of renewable energy — particularly wind — has challenged the Upper Midwest power grid, heightening the need for more transmission capacity. CapX2020 is providing that capacity, Mogensen said. More transmission lines will eventually be needed as wind power continues to grow, she said.

Last week, Xcel announced it would increase its wind power generation in the Upper Midwest over the next few years by 60 percent, adding eight to 10 wind farms and enough electricity to power about 750,000 homes.

Xcel has been the nation's leading utility for wind generation for more than a decade, and Minnesota ranks seventh among states in wind power production.

Mike Hughlett • 612-673-7003

about the writer

about the writer

Mike Hughlett

Reporter

Mike Hughlett covers energy and other topics for the Minnesota Star Tribune, where he has worked since 2010. Before that he was a reporter at newspapers in Chicago, St. Paul, New Orleans and Duluth.

See More