Citing numerous concerns, the city of St. Paul has asked Canadian Pacific Railway for more detailed answers about how its plans to expand a rail switching yard along the Mississippi River will affect the environment.
After weeks of reviewing the railroad's plans and taking comments from government agencies, advocacy groups and the public, the city announced Friday that it is requiring a full environmental impact statement (EIS) before approving a permit.
The decision puts the project on hold for the moment. The timeline for developing the EIS varies greatly, city planner Josh Williams said. The first step will be determining the questions about the project that need answering, a process that will be led by the city and include at least one public meeting.
Ed Greenberg, spokesman for Canadian Pacific, said the railroad was disappointed in the decision. Canadian Pacific, he added, has done its due diligence to address all environmental components associated with the project, which should reduce train congestion, locomotive idling and noise from switching operations.
Concerns for wetlands
The proposed expansion of what is known as the Dunn Yard — which entails adding six new tracks, lengthening them from 7,000 to 10,000 feet to accommodate longer trains and filling in more than 6 acres of wetlands along Pig's Eye Lake — "has the potential for significant environmental effects," the city said in a ruling signed by Kit Hadley, St. Paul's interim planning and economic development director.
The city is most concerned that the expansion will essentially fill in the wetlands around Pig's Eye Lake, which is fed by an inlet from the river. Wetlands are an important wildlife habitat that filter pollution and sediment and aid in flood control. Without the wetland buffer, both the lake and river could be affected, along with the river's flood plain.
The plan also would add an 880-foot retaining wall made of steel sheeting, ranging in height from 5½ to nearly 11 feet. Pilings to support the wall would be 23 to 43 feet deep. Canadian Pacific has said that groundwater could flow through seams in the wall and weep holes added to the pilings, but the city wants specific details on how effective those measures would be.
The railroad is required by law to replace the wetland at a 2-1 acreage ratio. It's proposing to buy wetland banking credits for its mitigation, documents show, rather than create or restore wetlands in the area.