CLEARBROOK, MINN. – Oil started flowing through the newly built Line 3 pipeline in northern Minnesota on Friday, bringing closure to one chapter of the large and bitterly disputed construction project.
Now comes a new one: cleaning up the mess left behind.
Forced by state regulators, Calgary, Alberta-based Enbridge has launched a major cleanup effort in Clearwater County to repair the aquifer crews punctured during construction in January. Artesian groundwater has been welling up for more than eight months near this rural community, wasting at least 24 million gallons and threatening to dry out two rare and protected wetland areas nearby called fens.
"I just don't want people losing precious water," said Jenna Olson, who works at the gas station in Clearbrook, population 464. "That's something serious."
The breach is a significant blunder on one of the largest construction projects in the state's recent history, but it's been largely out of public view given the location and the fact the company failed to tell regulators about it for several months.
The state Department of Natural Resources (DNR) revealed the problem only last month when it ordered Enbridge to pay $3.3 million for the damage and gave it 30 days to stop the uncontrolled flow of water.
Enbridge now faces an Oct. 15 deadline to essentially cork the artesian well it created. Its plan is to drill a new well to pump out some of the water and then inject tons of grout into the ground to try to seal it.
Clearwater County Attorney Kathryn Lorsbach said her office awaits the DNR's investigation reports, expected within weeks, to review for potential criminal charges.