U.S. Bank Stadium, the home of the Minnesota Vikings, will require some $280 million in maintenance to remain in top condition over the next decade, including nearly $48 million next year, according to an architectural assessment released Friday.
"Is there sufficient money to cover these? The answer to that is no," said Minnesota Sports Facilities Authority (MSFA) Chair Michael Vekich. "That is the work that we have to do collectively with [stadium operator] ASM, the Minnesota Vikings and ... the governor and the Legislature."
The Vikings and the public make annual contributions to the stadium capital improvement fund, which sits at just over $16 million. The audio-visual room — one of the areas that will need work soon — is alone expected to cost $14 million, the report said.
Kansas City-based Populous, an architectural firm specializing in stadiums and arenas, conducted the facility assessment on behalf of the MSFA, which oversees the seven-year-old building on behalf of Minnesota taxpayers. The MSFA paid $527,500 for the assessment.
Beginning in late December, Populous surveyed the building and found it to be in "very good shape" overall, according to senior principal architect Brady Spencer, who specializes in football stadiums and made the presentation to the MSFA meeting.
The assessment included estimates for maintenance, including an anticipated 4% annual escalation.
"Really the important thing about this is protecting your investment in the stadium," Spencer said.
Populous inspected the entire building, taking photographs to document the condition of everything from the concourses and structural steel to the zinc panels on the exterior. It also looked at all mechanical, electrical, plumbing and audio-visual systems.