Though the cost of the Southwest light-rail line has doubled to $2.7 billion over the past decade, the Metropolitan Council is still short more than $500 million to meet its budget, according to a special review released Friday by the nonpartisan Office of the Legislative Auditor.
It's unclear where the additional money — nearly 20% of Southwest's current budget — will come from, signaling a looming crisis for the state's most expensive public works project. The total price of the 14.5-mile line connecting Minneapolis to Eden Prairie has not been finalized, either.
Officials from Hennepin County, which has committed $1 billion to the project, told auditors that directing more money to Southwest would prove "challenging." The county has also made financial commitments to the Blue Line extension, another light-rail line in the works that will extend from Minneapolis to the northern suburbs.
The legislative auditor's 56-page report lays out only the facts surrounding the planning and construction of the Southwest line by the Met Council. Recommendations are expected next year.
One especially stark fact revealed in Friday's report: The Met Council purposely omitted from the bid package sent to potential contractors a station in Eden Prairie and a $93 million crash wall required by BNSF Railway to separate freight and light-rail trains in Minneapolis.
This meant the cost of these additions had to be largely be taken from the project's contingency budget — including a change order of nearly $83 million for the mile-long crash wall, west of Target Field. The cost of the Eden Prairie station was partly offset by a federal grant and funding from the city.
An unnamed Met Council official quoted in the report said there were concerns that including the two in the bid package would cause delays, possibly limit interest in the project from the construction community and result in higher costs.
"I think that is a huge red flag," said Rep. Frank Hornstein, DFL-Minneapolis, who pushed for the legislative auditor's review at the Legislature this year. "In the annals of public works projects, how could you put out a bid that doesn't include very, very key pieces of the project?"