Minnesota Vikings officials have agreed to provide analysts with more financial information on team owners Mark and Zygi Wilf, but fears continue to grow that construction of a new football stadium in downtown Minneapolis is falling behind schedule.
"I'm really concerned right now that 2½ years ahead of the opening, we're already looking at potentially a one-month delay," said Michele Kelm-Helgen, chairwoman of the Minnesota Sports Facilities Authority, the public board overseeing development of the $975 million stadium on the site of the Metrodome.
A public spat over the financial documents surfaced late last week. An attorney working on an audit, ordered after a New Jersey judge ruled earlier this month that the Wilfs had systematically defrauded partners in a real estate deal, said that despite "multiple requests" for the information, the Wilfs had, to date, "refused to provide us with any personal financial information."
That data, the lawyer said, was needed to assure the authority that the New Jersey court case, which could cost the Wilfs tens of millions in compensatory and punitive damages, wouldn't hurt the team's ability to help finance the stadium.
Kelm-Helgen said Monday that attorneys for the NFL club relented over the weekend, pledging to provide that paperwork. But Vikings officials also reiterated that they will not continue to negotiate critical stadium lease and development agreements until the authority's independent financial audit of the Wilfs is complete, potentially delaying construction and costing the project millions of dollars.
As of Monday afternoon, authority attorneys had yet to receive the information, Kelm-Helgen said. But, she added, "I am cautiously optimistic" it will be delivered.
Lester Bagley, the Vikings vice president for public affairs, said the team has already provided information with "more to come." Even then, however, it might not be enough to keep construction on track.
Kelm-Helgen said Mark Wilf told her Monday that the team has no intention of returning to the negotiating table to hammer out the lease and development agreements until the audit is complete, which could push back the construction timeline by a month.